IPG Photonics is the leading developer and manufacturer of high-performance fiber lasers and amplifiers for diverse applications in numerous markets. Avid Engineers has supported IPG throughout a 15 year partnership and has been responsible for the design of vast portions of IPG’s Oxford campus, including ground up designs for a number of new buildings on site.
One such building housed the Laser Testing & Application program. This design included the ground up construction of 3-story 65,000 SF facility with multiple testing and applications laboratories and assembly rooms, as well as sales and administrative offices with associated conference/meeting rooms. Included was the building support services – shipping/crating area, employee break room/ cafeteria, data center/server room, and connector corridors to existing adjacent buildings. The HVAC designs at IPG Photonics have included 750-ton water cooled, rotary screw chiller plants, 250-ton dry cooler farms and cooling tower relocations. Building-4 included 350-tons of self-contained air handling units. Temperature/humidity specifications were 65°F and 50% RH. The assembly/Testing and Research areas were classified as ISO 7 or 8 cleanroom space where pressurization gradients were maintained with process exhaust supported fume hoods, equipment evacuation processes, and canopies.